At 3:00 on December 24th, the 110-kilovolt Nanjing Lishui Kangyi Substation was officially put into operation. This substation was independently constructed by Lishui District Power Supply Company throughout the process. It is the first power grid infrastructure project in Nanjing to achieve local management, marking a crucial “first step of autonomy” for Lishui in power grid construction.

In recent years, with the successive implementation of key public welfare projects such as the Southern Campus of Nanjing Drum Tower Hospital and Nanjing Elderly Care Center, as well as the accelerated aggregation of strategic emerging industries like high-end manufacturing and new energy in Lishui Development Zone, the regional electricity demand has continued to rise. The original 35-kilovolt Qunli Substation is no longer capable of meeting the development needs. The construction and operation of the Kangyi Substation have become an important measure to ensure regional power supply and serve social welfare.

Kangyi Substation is located in
At the intersection of Changle Avenue and Qunli Avenue
Construction was officially launched in October last year
Two 50,000-kilovolt-ampere main transformers are equipped in the station
Two 110-kilovolt transmission lines and their supporting facilities
It will be significantly improved after operation
The power supply capacity of the northern part of Lishui Development Zone and the Qunli area
Effectively meet the electricity demands of residents’ daily life and enterprises’ production
It will also be for distributed photovoltaic power
Provide grid connection support for new energy projects such as energy storage
Support the development of regional green energy

From planning to operation, the entire process of this project was independently implemented by Lishui District Power Supply Company. Project Manager Zeng Min introduced, “This is the first time we have independently undertaken the construction task of a substation of this scale.” We have formed a professional team to fully control each link from design, construction to acceptance, ensuring the quality of the project. During the construction process, the power supply department closely collaborated with relevant government departments, efficiently resolving practical issues such as the implementation of the plan and the coordination of lines, demonstrating the synergy of government-enterprise collaboration in serving development.

The successful operation of Kangyi Substation
For the independent construction of county-level power grids
It provides replicable practical experience
Lishui District Power Supply Company will continue
Deepen the reform of the power grid construction model
With a stronger and more reliable power grid
More high-quality and efficient services
Inject stronger power impetus into the high-quality development of Lishui